The Grand Pier Weston super Mare

Due to re-open in the summer of 2010, the Grand Pier is closed for the re-construction of a brand new state of the art pavilion. Please visit regularly for updates and press releases regarding the Pavilion re-build. Thank you for your support.


Weather Allows Work to Continue

19th January 2010


After three weeks of waiting, the weather finally thawed last Friday and made it possible for the first concrete to be poured on the Grand Pier since the re-build started last September. Concrete was pumped from the shore along the entire length of the waist and contractors were able to create the floor of the 3rd floor plant room and the 250 seater conference room at the front of the second floor overlooking the town.

A relieved Richard Sutton of John Sisk & Co, the Main Contractor said, "we have been waiting for over three weeks for the weather to break so we could pour the concrete, if it wasn't bad enough having to pump it a quarter of a mile, the inclement weather meant it kept freezing before it got to where we needed it. We are pleased to have finally managed to get it out there and weather permitting, we hope to do another large pour next Wednesday".

Visitors to the seafront can now see the beginning of a 100-metre long and 20 metre high scaffolding ramp being created in front of the new Pavilion. This is to give access so the roof sheets can be rolled at the shore in one piece and carried along the waist and onto the roof. Each piece is over 80 metres long, this is to ensure that there are no joins that could give rise to troublesome leaks in the future.

They are usually rolled and lifted straight onto the roof but the machine that is used weighs more than 25 tons and cannot be taken onto the Pier so the sheets will have to be carried out and lifted into place by hand. Owner Kerry Michael said, "this is just one of the many logistical problems we have had to overcome on this project. I can only applaud the way the contractors (John Sisk) continue to overcome the unique challenges that are being thrown at them. Let's hope the worst of the weather is now behind us and we can manage to claw back the lost time".


Panoramic Tower Delay

8th January 2010


The Panoramic Tower at the Grand Pier won’t be ready in time for the re-opening this summer. The deal with the original Italian suppliers fell through and despite sourcing a new supplier, delivery date guarantees were not forthcoming.

Kerry Michael said, "we have to be open as soon as possible and we are not prepared to risk a delay to the re-opening for the sake of the tower. Therefore, we will open as planned and continue our negotiations with the new manufacturer so that we can have the tower in place for the following season. We are still committed to delivering it as promised but we need to make sure everything is right, for example, the foundations that are already in place were designed for the original tower and are likely to require modification and because the design is slightly different, we may even require an amendment to our planning permission and there is simply not enough time to do this and meet the re-opening date this summer.

Although the current weather conditions are providing their own challenges for us, we are confident that The Grand Pier will re-open on time and we cannot let anything affect that. We will still have 18 brand new rides and attractions for everyone to enjoy and the tower will give us all something to look forward to the following summer season."


On track for summer opening

5th January 2010


The Grand Pier rebuild has progressed well over the Christmas period. The steel forming the upper floors has been installed and although not yet waterproof, most of the roof sheeting has also been installed. The general shape of the building and towers is now clearly visible.

Kerry Michael said, "The weather is quite kind to us at the moment without much wind, however the cold weather means that we cannot pour concrete to create the floors. Hopefully if we get a break in the cold weather next week, we can catch up then.

The large floating barge and crane have completed their work and have now left site. The remaining works will be completed using the spud leg barge, although we will probably need the big barge back again to erect the Panoramic Tower when that is delivered."


The Re-build Continues!

22nd December 2009


The Grand Pier Pavilion re-build continues at pace with this week seeing the cladding to the southern elevation being completed, the northern elevation more than half way complete and work has also started on cladding the towers. Also, the roof is almost completely covered with the 'under sheet' that sits beneath the final waterproof sheeting of the main roofs.

The metal floors creating the first and second levels are in place and ready for the concrete to be poured early in the New Year.

Kerry Michael said, 'we are pleased with the progress we are making however we have slipped a little due to the adverse weather throughout December. We are hopeful to make up any lost time as soon as the building is fully enclosed and in the dry. It's taking shape now and for the first time you can see the outline and scale of the new Pavilion. The response from the public has been fantastic as the building goes up and we are all very encouraged by the support we are receiving'.


Watch the rebuild on our new Grand Pier Webcam


The Re-build is Racing Ahead!

14th December 2009


The Grand Pier re-build is racing ahead. Most of the structural steelwork for the Main Pavilion has now been erected and contractors are starting on the new building which is going on the Pier head. The large steel panels that cover the entire surface area of the Pavilion creating the new floor have also now been installed.

The first roof sheets are going on and cladding has started to the north elevation. Progress with this should significantly increase this week as a number of additional staff have been drafted in to speed up the build. The front of the new building has been scaffolded to facilitate access.

Weston super Mare's Grand Pier RebuildWeston super Mare's Grand Pier Rebuild

Pier owner Kerry Michael said, ‘although contractors have been working for most of this year, their work was mostly beneath the deck and it’s only now that the building is springing up above the deck that people can actually see what’s happening.

We are receiving hundreds of letters and emails every week and the web cam hits are growing every single day so people are really noticing what’s going on. We expect to carry on making good progress and we are confident of achieving our opening date, the only threat is the weather but the last few days have been good for us.


Creative thinking needed to solve Grand Pier challenges

11th November 2009


How do you get a 60 tonne crane onto a jack up barge that is 240m out to sea and is 30 times too heavy to move down the Pier?

You build a ramp, 20 metres long and 3 metres high out of sand to allow the crane to drive from the last point of the shore that it can reach, to the barge.

The new “jack-up” barge was tested this week to make sure that it can be properly secured in the Weston mud. With this test successfully passed, the ramp will now be created with 2 diggers and 2 dumpers taking sand from inside the Grand Pier fence line. After the crane has reached the safety of the barge, the sand will be replaced.

Joint owner of the Pier Kerry Michael said: “This is one of many creative solutions that we have had to come up with to solve the challenges that are created in building this extraordinary Pier. I’m sure there will be many more improvisations before we are finished!”

Richard Sutton is the Senior Contracts Manager for main contractor John Sisk. He said: “We have checked with Natural England about moving the sand and they have given us the all clear as there will be no problem or harm to the environment. The ramp was the quickest method to put the crane on the barge.”


Happy birthday Grand Pier!

5th November 2009


The Grand Pier in Weston-super-Mare will quietly celebrate its 106th birthday on Saturday. On 7th November 1903 work started on the building of the original Grand Pier. The contractors were Mayoh & Hayley of London. The celebration will be low-key because the focus of the company is directed completely towards the rebuilding.

The Grand Pier always has a bursting email box with followers from around the world. Recently received was an email from Anne Mayoh, the grand-daughter of Arthur Mayoh, of Mayoh & Hayley. Anne is also the daughter of Karl Mayoh who worked on the Pier in 1931. She now lives in Australia.

Kerry Michael, owner of the Grand Pier said: “We were so pleased that Anne got in touch with us as we love receiving interesting items for our social history files. I have invited Anne and her husband to attend one of our opening events and I very much hope she will visit the new Pier and be impressed by our work.”


Read all about it!

4th November 2009


The story of Weston-super-Mare’s Grand Pier will start unfolding along the seafront hoardings surrounding the Pier’s building site from next Thursday (12th November). The 180 square meters of hoardings are currently painted white but soon will show a complete time-line of the Pier, following its history from the original opening in 1904 to the present day.

Pier Owner Kerry Michael said: “These barren hoardings will soon be brought to life. The design is packed with information, facts and figures, photographs, history and fun. It will make the walk along that part of the seafront more interesting as there will be something for everyone to enjoy. A special children’s area has been created and “peep holes” will be cut into the design so everyone can see what is going on. We wanted the design up in time for the Carnival.”

The designs have been produced by the Grand Pier using its own archive material and items sent in from the public. Some reproductions, such as a front page of the Weston & Somerset Mercury showing pictures of the 2008 fire will also appear. The designs will be digitally printed on pvc banner material and produced in 10 ft lengths.


The Grand Pier, Weston-super-Mare - going up!

26th October 2009


Work has started this morning (Monday), erecting the frame of the new Pavilion building on Weston's Grand Pier. More than 100 tonnes of steel per week will be used to form the structure of the new building. In total more than 1,100 tonnes of steel is being supplied by local firm Hayley Engineering for the project. This means that the appearance of the Pier will start to change quickly now that the first columns are in place. The specially constructed structural floor is still being laid and this work will continue keeping just ahead of the framing works. The roof lining and cladding will start once the front section of the building frame is erected which is scheduled before the end of November.

Pier owner Kerry Michael said, "Following months of hard work by all the design team and more than £9million having been invested to date, we are delighted to see the building rising above the deck. We are all looking forward to when it is watertight so we can start installing all the fabulous rides and attractions we have gathered together from all around the World. Next June and the re-opening can't come soon enough".


The Grand Pier moves into constructive phase

23rd October 2009

Weston super Mare's Grand Pier Aerial View

After £9 million has been spent on clearing the debris, driving in piles and making good the basic structure of the Pier, visible construction has now started.

In the last three weeks, approximately one third of the structural metal decking units have been laid. The metal decking units, made from polyurethane sandwiched in between 5mm steel sheets, are usually used in ship building. They are nearly 10 metres long and 2 metres wide and are being placed on to new structural steels to form the deck of the Pier’s new main pavilion.

Read full story.....

Weston on the map for trade visit

16th October 2009

BALPPA visit the Grand Pier Weston super Mare

A record turn out of over 100 members of the UK’s largest leisure industry association representing commercial leisure parks, piers, zoos and static attractions sector visited the West Country yesterday.

BALPPA, the British Association of Leisure Parks, Piers and Attractions visited Wookey Hole, Bristol Zoo and Brean Leisure Park before moving onto Weston where the group has not been for over 17 years. In Weston, the members had a sumptuous 3-course lunch at the Thatched Cottage Restaurant on Weston super Mare's seafront and a presentation on the rebuilding of the Pier from Kerry Michael, joint owner of the Pier. The group then took a tour of the Pier building site.

Read full story.....

Churchill School students on Grand Pier mission

12th October 2009

Churchill School Students on Grand Pier mission

Five A2 level product design students from Churchill School received special permission to go onto the Grand Pier building site as background for their design projects.

Read full story.....

Safe haven for Grand Pier barges

06th October 2009


A new deep-water anchor site at Brean Down is being arranged for Weston’s Grand Pier barges so that they can take cover close by when bad weather threatens.

Read full story.....

Grand Pier finds solution to latest weather problem

1st October 2009

Barge at the Grand Pier Weston super Mare

With force 8 gales predicted over the next few days, the first barge working on the Grand Pier will be moved today to Cardiff docks and return on Monday 5th October, weather permitting.

Although this will slow down the progress this week on the decking that is currently being laid, a solution has been found so that work will be able to press ahead and keep on track.

Read full story.....

The Grand Pier’s got talent

07th September 2009


When the WSM STREETFEST hits town on Saturday 19th and Sunday 20th September opposite the Tropicana, there will be plenty of scope to show off your dance moves.

Read full story.....

Contractor to rebuild Weston Pier announced

05th August 2009


The contractor to rebuild the new pavilion at Weston-super-Mare’s historic pier has been appointed.

With the piling work now complete and the enabling work to strengthen the pier structure progressing, John Sisk & Son will now start work as soon as possible to restore the historic tourist attraction that was burnt down in a devastating fire on 28 July 2008.

Read full story.....

Grand Pier - One year on

28th July 2009

Grand pier Fire

The first anniversary of the fire that destroyed Weston-super-Mare’s Grand Pier sees the structural rebuilding work completed and the pier now ready for its new pavilion to be created.

The devastating blaze on the morning of July 28, 2008 will never be forgotten by those who witnessed it and the pier fire made headlines all around the world with over three million people watching footage of the destruction online.

Read full story.....

Grand Pier Webcam

The Grand Pier webcam shows the changes as work takes place to rebuild it after the devastating fire on July 28, 2008.

Launch webcam.....

You can find us on the following websites too:


BlogSpot Facebook Twitter You Tube Trip Advisor

The Grand Pier on Facebook

Grand Pier Blog
Tweeting on Twitter
Garden Centre
Whats On Weston Super Mare supports the Grand Pier

Can You Help Us?


Pictures, stories, memorabilia, ideas?

A huge collection of the Grand Pier's history was lost in the Pavilion fire and we would like replace as much as we can.

If you have any pictures, stories or memorabilia regarding the Grand Pier, old or new we would be extremely grateful if you could get in touch. Please call or email us via the contact page.


Link To The Grand Pier Website


If you like our website, please link to us

If you would like to link to us, please use the following code:

Grand Pier Weston super Mare - All year round attraction with spectacular views and brand new state of the art rides.